If 2 men or 3 boys take 40 days to complete a piece of work , how long will 4 men and 9 boys working together take to complete the same work

Answers

Answered by ayushraj8928
0

Answer:

no idea you have complete this answers

Answered by prempaharia12
1

Answer:

20 days

Step-by-step explanation:

No. Of people is double so no. Of days is divided by 2