if 20 man complete a wark in 8 days, then how many days can 8 man??​

Answers

Answered by khushishukla82
2

Answer:

20 days and ur work spelling is wrong

Answered by RAJNEESH132
1

20×8=y×8

160=y×8

160/8=y

20=y