If 20 men assemble 8 machines in a day , how many are needed to assemble 12 machines in a day ? Direct Variation question.
Answers
Answered by
19
30 men are needed to assemble 12 machines in a day.
Step-by-step explanation:
Let of no. of men required to assemble 12 machines per day be x
Given,
No. of machines to be assembled = 8, 12
No. of men required = 20, x
Using Direct Variation,
x1 / x2 = w1/ w2
8/20 = 12/x
8x = 240
x = 240/8
x = 30
∵ 30 men would be required to assemble 12 machines per day.
Learn more: Direct Variation Method
brainly.in/question/1096516
Answered by
7
Answer:
30
Step-by-step explanation:
=
BY CROSS MULTIPLICCATION-
20*12=8X
240=8X
X=240/8
X=30