If 20 men can complete a work in 40 days, then when should 4 men leave the work so that the whole work can be completed in 48 days?
Answers
Answered by
1
Answer:
The total number of days require to complete the work =20×40=800 days.
i.e. a single man can complete the work in 800 days.
Let x be the number of days after which 4 men leave the work.
So,
20x+16(48−x)=800
or, 20x+768−16x=800
or, 4x=32
or, x=8
Hence, If 4 men leave the work after 8 days it may be finished in 48 days.