Math, asked by rajgazmer84, 1 day ago

if 20 men can complete a work in 8 days then 10 men can complete half of that work in (a) 32 days (b) 8 days (c) 10 days (d) 2 days​

Answers

Answered by dayanidhisharma19
1

Answer: 10 men can complete half of that work in 2 day's.

Please see the attached document for step by step explanation.

Step-by-step explanation:

Attachments:
Answered by sheeb12ansari
0

Given: 20men can complete a work in 8days.

We have to find the number of days required for 10men to complete half of that work.

We are solving in the following way:

Let the number of days taken by 10men will be'x'

we have,

20men can complete work in 8days.

From the given statement, we can write:

\frac{20}{10} =\frac{8}{x}

=>20\times x=8\times10\\=>20x=80\\\\=>x=\frac{80}{20} \\\\=>x=4

Hence, 10men can complete work in 4days.

Now, the number of days required to 10men to complete half of that work will be:

=>\frac{x}{2} \\\\=>\frac{4}{2} \\\\=>2

Hence, 10men will take 2days to complete half of that work.