Math, asked by Anonymous, 9 months ago

if 20 men can do a piece of work in 45 days then how many men will be required to do it in 25 days

Answers

Answered by yashika7011
1

Answer:

45 days =20men

1 day=20/45

25 days=20/45×25=11 men