Math, asked by prisha1712, 10 months ago

if 20 men can do work in 12 day how many more are needed to do the same work in 8 days ​

Answers

Answered by mukhtar6165
1
It is in inverse proportion.10 more men are required.
Attachments:

tishya39: it can't be inverse
tishya39: because in inverse one thing increase and another decrease
mukhtar6165: As the number of men increase the time taken will decrease.
Answered by tishya39
1

20 men in 12 days

?men in 8 days

then

 \frac{20}{12}  =  \frac{x}{8}

therefore ans would be 12x=160

x=13.3.....


mukhtar6165: 13.3 men are required?
mukhtar6165: How (point) men will do the work.