If 20 men complete a piece of work in 12 days , how long will 40 men take to do the same piece of work? Solve with ratio and proportion method .I know the answer but I want the process.
Answer is 6 Days
Plzzzzzzz fast
Answers
Answered by
26
20:12::40:Day
20/12=40/Day
Day=12*20/40
= 6
20/12=40/Day
Day=12*20/40
= 6
Answered by
7
20 men complete 12days, 40 men how many day ?
Solution
(20*12)/40 = 6days