Math, asked by mounibeauty732, 11 months ago

If 20 men do a work in 25 days 5 men can do the same work in

Answers

Answered by sadhya15
5
5 men can complete the work in ...........
20×25/5=100 ans.....
thanks hope it will help you......
Answered by Abdulrahman12
0
hay freind here is your answer
If the W1 number of workers take time T1 to complete the work and W2 number of workers take time T2 to complete the same amount of work, then
W1 :W2 = inverse of T1 : T2
or W1 : W2 :: T2: T1
assume T2 = x
20 : 5 : : X: 25
5X =20 × 25
X = 20 × 25/5
X = 20×5
X = 100 Days
I hope it is true