If 20 men working 8 hours per day can complete a piece of work in 21 days. How many hours per day must 48 men work to complete the same job in 7 days?
A) 12 B) 20 C) 10 D) 15
Answers
Answered by
0
Step-by-step explanation:
Given
- 20 men working 8 hours per day can complete a piece of work in 21 days
To Find :-
- How many hours per day must 48 men work to complete the same job in 7 days?
Answer :-
- 15
Answered by
0
Answer:
Hey mate here is your answer ⬇️
Option d=15