If 20 men working 8 hours per day can complete a piece of work in 21 days. How many hours per day must 48 men work to complete the same job in 7 days?

A) 12 B) 20 C) 10 D) 15

Answers

Answered by Anonymous
0

Step-by-step explanation:

Given

  • 20 men working 8 hours per day can complete a piece of work in 21 days

To Find :-

  • How many hours per day must 48 men work to complete the same job in 7 days?

Answer :-

  • 15

Answered by 2ndiidoofTHOR940
0

Answer:

Hey mate here is your answer ⬇️

Option d=15