Math, asked by malavikaboddula, 1 month ago

If 20 men working 8 hours per day can complete a piece of work in 21 days. How many hours per day
must 48 men work to complete the same job in 7 days?
15
UX010142
12 20
10​

Answers

Answered by asahilthakur
1

Answer:

10

Step-by-step explanation:

The number of men and the time taken to complete the same work are inversely proportional. In inverse proportion, the product remains constant.

Let the number of hours per day be h.

=> 20 × 8 × 21 = 48 × h × 7

=> h = 10

Therefore, they should work for 10 hours per day to complete the same job in 7 days.

Answered by tonystarky247
1

Answer:

10 hrs per day

Step-by-step explanation:

20 men finish works in = 21 days

48 men finish works in = (21 × 20) / 48 = 35/4 days

Now,

Their 8 hrs work finish in = 35/4 days

Their 1 hr work finish in = 35/4 × 8 = 70 days

Their 10 hr work finish in = 70/10 = 7 days

So,, they have to work for 10 hrs per day

Hope it helped!