If 20 men working 9 hours a day can finish work in 18 days, in how many days will 27 men working 10 hours a day complete the same work
Answers
Answered by
1
Answer:
M1*D1*T1 = M2*D2*T2
20*18*9 = 27*X*10
X = 12 days . (Ans.)