If 20 men working together can finish a job in 20 days, then the no. Of days taken by 25 men of the same capacity to finish the job is ___________?
Answers
Answered by
8
Answer:
16 days
Step-by-step explanation:
days taken by 20 men = 20 days
days taken by 1 men =20×20
400 days
days taken by 25 men= 400÷25
=16 days
hope this helps you.....
✌️✌️✌️✌️