If 20 men working together can finish a job in 20 days then how many days will be taken by 25 men if the same capacity to finish the job.
Answers
Answered by
4
Answer:
Using Work=men×days we get
Work=20×20
Work=400
Now, work is same and number of days are to be calculated
400=25×days
days=16
gunnu1963:
Thank you
Answered by
0
Answer:
Using Work=men×days we get
Work=20×20
Work=400
Now, work is same and number of days are to be calculated
400=25×days
days=16