Math, asked by nandini0014, 3 months ago

if 20 workers can carry out a project in 15 days. how many workers will be needed complete in 30 days.​

Answers

Answered by Anureet25
1
20 workers are needed to carry out the work in 15 days.
As 30 is the double of 15 the number of workers will reduce by half.
Therefore, 10 workers are needed to carry out the work in 30 days.

This can also be done by unitary method—
20 workers—->15 days
30 workers 20/30x15days=10 days
Answered by valmetijananya
0

Answer:

40 workers will be needed to carry out the project in 30 days

Thamq

Rate my answer and also like it if it helped u

Similar questions