If 20 workers can complete a work in 6 days how long will 12 workers take to finish the same work ?
Answers
Answered by
1
Answer:
10 days
Step-by-step explanation:
20 workers can complete work in =6 days
1 worker can complete work in = 20×6 days
12 workers can complete work in= 20×6÷12=10 days
hope this helps you