if 20 workers can do a piece of work in 48 hours.how many members can finish same work in 32 hour
Answers
Answered by
2
Answer :-
30 workers
step by step solution :-
if 20 workers can do a work in 48 hrs
how many workers we should need to do a work in 32 hrs
48 hrs ----- 20 workers
1 hrs ------ (20 × 48 ) workers
32 hrs ------ 20 × 48 /32
20 × 3 / 2
10 × 3 = 30 workers
hence to get our work done in 32 hrs we need 30 workers