Math, asked by sriramchiluveru122, 3 months ago

 If 20 workers can finish the work in 10 days how many days will it take for 8 workers to complete the same work​

Answers

Answered by araziq522
0

Answer:

25 days

Step-by-step explanation:

if you find helpful please show me brilliant

Attachments:
Similar questions
Math, 9 months ago