Math, asked by khusbubarakoti, 10 hours ago

If 200 men can make an embankment 5kms long in 25 days, how much overtime per day must 60 men work to finish an embankment 2km long in 32 days? 12 hours being a day's work.
ANS:1/2 hrs.​