If 21 man build a dam in 2 month 24 days, in how much time will 42 men build the same dam?solution fast
Answers
Answered by
2
Answer:
2 month 24 day = ( 2 × 30 ) + 24 = 84 days
If 21 men build a dam in 84 day
then, one man build the same dam in (21×84) days
42 men build the same dam in day = (21×84)/42
=> 21 × 2 = 42 days
Hence, 42 men build the same dam in 42 days or 1 month 12 day
I take 1 month = 30 day because in math question when there is not given year or
month name. Then we should take normally
1 month = 30 days
I hope it's help you please mark me as brainlist.
'' keep learning my dear friend ''