Math, asked by sumanreignsm, 2 months ago

if 21 men can do a job 10days,how many men required to do the job in 15days?​

Answers

Answered by adiwan2
0

Answer:

14

Step-by-step explanation:

21*10=15*x

x=14

Answered by sayan3463
0

Answer:

14

Step-by-step explanation:

We have,

No. of men to finish the work in 10 days = 21

No. of men to finish the work in 1 day = 21 × 10

No. of men to finish the work in 15 days = 21 × 10/15

                                                                   = 21 × 2/3

                                                                   = 7 × 2

                                                                   = 14  

Hence 14 men are required to complete the work in 15 days.