If 22 boys working together can finish a job in 105 days, then the number of days taken by 55 boys
of the same capacity to finish 3 such jobs is:
A. 126 days
B. 128 days
C. 130 days
D. 132 days
Answers
Answered by
5
Answer:
A. 126 days
Step-by-step explanation:
22 boys complete a job in 105 days
55 boys complete a job in 105*22/55 days=42 days
55 boys complete 3 such jobs in 42*3 days = 126 days
Answered by
1
Answer:
126 days option (A) Option B,C,D is wrong