Math, asked by avishat, 5 months ago

if 22 men can dig 13(1/2) long canal in a day , how many men should be employed for digging 20(1/4) metre long canal of the same type in on day​

Answers

Answered by reyyakalyani
1

Step-by-step explanation:

Men : Length trench :: Men : Length of trench

22 : 27 m :: x : 135 m

X = (22 135)/27 = 110 men