Math, asked by chinkimondal03, 2 days ago

if 24 kids can complete a piece of work in 42 days. How many workers should be added to complete the same work in 18 days?​

Answers

Answered by khanakprakash091985
2

Step-by-step explanation:

may this help you

please leave a vote

Attachments:
Answered by meenaindra105
1

Answer:

No of kids No. of days

24 42

y 18

24×42=18×y

y = 24 × 42/18 = 56

hence, answer is 56