if 24 man can finish a piece of work in 15 days,than how many man will be needed to finish it in 20 days
Answers
Answered by
2
Answer:Let x be the person required
This is an inverse variation, the product remains the constant
24×15=X×20
360=X×20
X= 360÷ 20
X=18
Step-by-step explanation: