If 24 men can do a piece of work in 15 days working 8 hours per day, then how many men will be required to do the same work in 10 days working 6 hours per day
Answers
Answered by
1
Answer:
man. days. hrs
24. 15. 8
x. 10. 6
x=15/10 X8/6x24=48 men
Addl.24 men
Similar questions
Math,
5 months ago
Physics,
5 months ago
English,
5 months ago
Social Sciences,
10 months ago
Social Sciences,
10 months ago
Math,
1 year ago
Science,
1 year ago