if 24 men can do a piece of work in 36 days in how many days will 54 men do it?​

Answers

Answered by nysasureka2005
0
If 24 men can do the work in 36 days
Then 1 man can do the work in 36/24=1.5 days
Therefore 54 men can the the work in 1.5* 54= 81 days


Answer- 54 men can do the piece of work in 81 days