If 24 men can do a piece of work in 40 days working 12 hours a day, then how many men are required to complete the double work working 6 hours a day in 20 days?
Answers
Answered by
1
Step-by-step explanation:
15 member they can wear for 6 hours a day can work up to 20 days this like up to 6 hours only
Answered by
0
In 40 d working 12 hrs 1 work is done by 24 m
" 1. " " " " " " " " " 24*40 m
" " " " " " 1 " " " " 24*40*12m " 20 " " " " " " " " " 24*40*12/20m
" " " " " " 6 " " " " 24*40*12/20*6m
" " " " " " " " 2. " " 24*40*12*2/20*6m
= 192 men(answer).
Hope you would understand and your concept is clear and if you liked it, then please mark it as the brainliest answer.