If 24 men can finish a piece of work in 15 days.how many men will be needed to finish it in 40 days
Answers
Answered by
0
Answer:
15 days required to finished the work for 24 men
1 days required to finished the work for 24×15 men
40 days required to finished the work for
24×15/40 men=9 men
so, 9 men will be needed to finished the work in 40 days
Answered by
17
Hence, 64 men are needed to complete the work in 40days