English, asked by swapnalinikam, 12 days ago

If 24 mes can finish a work in 10 days, then find the
No. of days beq. to complete the same work by 30 men ?
day​

Answers

Answered by muhilan975132
0

Explanation:

this is the answer

please make brinlyest answer

Attachments:
Answered by shanawar0324
0

Answer:

8days

Explanation:

 \frac{24}{30} =  \frac{x}{10}  \\24 \times 10 = x \times 30 \\ 240 = 30x \\  \frac{240}{30}  = x \\ 8 = x