if 25 equally skilled workers can earn ₹135000 in 30 days working 4 hours a day. then in how many days will the total wages of 48 workers be ₹ 1,55,520. if they work for 6 hours a day
Answers
workers and wages direct relation
workers and number of days and hours indirect relation..
(workers×days×hours)/wages = constant..
let 'D' be required number of days
(25×30×4)/135000 = (48×D×6)/155520
D=12days..
It will take 12 days for 48 workers.
Step-by-step explanation:
Since we have given that
Number of skilled workers = 25
Number of days = 30 days
Number of hours = 4
Amount earned = Rs. 13500
If the number of workers = 48
Amount earned = Rs. 155520
Number of hours = 6
Using "Time and work rule"
So, it becomes,
Hence, it will take 12 days for 48 workers.
# learn more:
12. If 36 equally skilled workers can earn 2,49,480 in 18 days working 7 hours a
day, then how many hours a day should 52 workers work so that their total wages
in 32 days will be 7,32,160 ?
https://brainly.in/question/13103423