if 25 laboursworking 6 hours a day can finish a piece of work in 12 days how many labourers working 5 days are they can finish it in 30 days
Answers
Answered by
2
Answer:
12 men
Step-by-step explanation:
let men required be x
x=(25*6*12)/(5*30)
= 12 men