If 25 men can do a piece of work in 24 days, how many men would be sufficient to do
it in 20 days ?
Answers
Answered by
0
Answer:
30 mens hope its helps you
Answered by
0
Solution-
25men * 24days = x men * 20days
25 x 24 / 20 = 30men
25men * 24days = x men * 20days
25 x 24 / 20 = 30men