Math, asked by class5chinmay, 4 months ago

If 25 men can do a piece of work in 24 days, how many men would be sufficient to do
it in 20 days ?​

Answers

Answered by rami9024
0

Answer:

30 mens hope its helps you

Answered by prashantpsc007
0
Solution-
25men * 24days = x men * 20days
25 x 24 / 20 = 30men
Similar questions