Math, asked by tanveer5629, 8 months ago

If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days? ​

Answers

Answered by NewBornTigerYT
0

\huge{\fbox{\fbox{\orange{\mathfrak{Answer\::}}}}}

75 men

number \: of \: men \times  \frac{1}{number \: of \: days \:  \times  \: time}

➡️So, given 25 men × 36 days × 10hours

➡️If the number of men=x

&duration is 6 hrs/day and complete it in 20 days.

25 \times 36 \times 10 =  x \times 20 \times 6

➡️cancel the digit by transposing to LHS.

\huge{\fbox{\mathfrak{x = 75}}}

So, the workers required to complete the work is 75 men

Answered by jenisha145
0

75 men are required to do the same work

Step-by-step explanation:

Given:

25 men can do a piece of work in 36 days by working 10 hours a day

To find:

number of men required to complete the same work in 6 hours a day in 20 days

Solution:

Let's say,

M_{1} = men required initially = 25

D_{1}= days required intially = 36

h_{1}= hours required intially = 10

D_{2}= days required later = 20

h_{2}= hours required later= 6

m_{2}=?

As we know the work is same both the times

Using the ratio & proportion concept

Thus, \frac{{m_{1}d_{1} h_{1}  } }{w_{1} } =\frac{{m_{2}d_{2} h_{2}  } }{w_{2} }

{{(25)} (36) (10)}  } }={{m_{2} (20) (6)  } } }

9000 = m_{2} (120)

\frac{9000}{120} = m_{2}

m_{2}=\frac{9000}{120}

m_{2}=75

m2 = 75

Thus, 75 men are required to complete the work by working 6 hours a day for 20 days.

#SPJ2

Similar questions