If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
Answers
Answered by
0
75 men
➡
➡️So, given 25 men × 36 days × 10hours
➡️If the number of men=x
&duration is 6 hrs/day and complete it in 20 days.
➡️cancel the digit by transposing to LHS.
So, the workers required to complete the work is 75 men
Answered by
0
75 men are required to do the same work
Step-by-step explanation:
Given:
25 men can do a piece of work in 36 days by working 10 hours a day
To find:
number of men required to complete the same work in 6 hours a day in 20 days
Solution:
Let's say,
= men required initially = 25
= days required intially = 36
= hours required intially = 10
= days required later = 20
= hours required later= 6
=?
As we know the work is same both the times
Using the ratio & proportion concept
Thus,
∴
∴
∴
∴
∴
m2 = 75
Thus, 75 men are required to complete the work by working 6 hours a day for 20 days.
#SPJ2
Similar questions