If 25 men take 40 days to complete
a piece of
work, how long will 20 men take to complete the
same work​

Answers

Answered by arpanghosh25
1

Answer:

1 man takes how many days to complete a work= (25×40)days= 1000days. 20 men takes how many days to complete a work= (1000/20)days = 50 days.

Answered by student6095
0

32 days .