if 25 men take 40days to complete a piece of work how long will 20 men take to complete the same work. please help its my exam please
Answers
Answered by
4
Answer:
50 days is the answer.
good luck for your examination.
Step-by-step explanation:
25 men takes how many days to complete a work = 40days.
1 man takes how many days to complete a work= (25×40)days= 1000days.
20 men takes how many days to complete a work= (1000/20)days = 50 days.
Answered by
0
Answer:
50 days will be taken by 20 men to complete the task
Step-by-step explanation:
25 men takes how many days to complete a work = 40days.
1 man takes how many days to complete a work= (25×40)days= 1000days.
20 men takes how many days to complete a work= (1000/20)days = 50 days.
For similar questions refer-https://brainly.in/question/31628169
#SPJ5