If 25 men, working 8 hours a day, can reap a field in 20 days, then in how many days will 16 men reap the field, working 10 hours a day?
please solve
Answers
Answer:
If 25 men working for 8 hours a day can reap a field in 20 days
The total work for reaping the field is
= 25 men × 8 hours × 20 days
= 4000 man-hour-days.
How many days will it take 18 men to reap the field if they work for 8 hours a day?
Work done by 16 men working 10 hours a day
= 16 men × 10 hours
= 160 man-hours
Number of days the work will be completed
= Total work in terms of men-hour-days / men hours available
= 4000 men-hour-days / 160 men - hours
= 25days. is the correct answer.
Answer:
If 15 men working for 9 hours a day can reap a field in 16 days, how many days will it take 18 men to reap the field if they work for 8 hours a day?
Friends…!
If 15 men working for 9 hours a day can reap a field in 16 days
The total work for reaping the field is
= 15 men × 9 hours × 16 days
= 2160 man-hour-days
How many days will it take 18 men to reap the field if they work for 8 hours a day?
Work done by 18 men working 8 hours a day
= 18 men × 8 hours
= 144 man-hours
Number of days the work will be completed
= Total work in terms of men-hour-days / men hours available
= 2160 men-hour-days / 144 men - hours
= 15 days