if 25 person can Dig a treach 36m long in one day, then find the number of a person required a treach 108 m long in one day
Answers
Answered by
2
Step-by-step explanation:
please mark me as brainlest and also follow me please
Attachments:
Answered by
2
Answer:
No. of persons required to dig a trench 108m long in one day be x.
Persons = 25 x
Trench = 36 108
Clearly it is a case of direct variation.
25 × 108 = 36x
2700 = 36x
x = 75
75 persons are required.
I hope this will be help you.