if 25 persons can dig a trench 36m long in one day , then find the number of persons required to a dig trench 108m long in one day
Answers
Answered by
2
Answer:
75 persons
Step-by-step explanation:
We can find it by using Unitary method :-
36m long trench can be dug by = 25 persons
1m long trench can be dug by = 25/36 persons
108m long trench can be dug by = 25/36 x 108
= 75 persons