If 25 workers can finish a job in 40 days , hiw many worker will complete the same job in 25 days ?
Answers
Answered by
1
The job can be finished in 40 days by 25 workers
The job can be finished in 1 day by 25×40 workers
The job can be finished in 25 days by 25×40/25 workers
=40 workers
Answered by
1
Step-by-step explanation:
25 workers can finish a job in 40 days
worker will complete the same job in 25 day =
workers complete the job in 1days = 25*40
workers complete the job in 25days = (25*40)/25= 40 workers