Math, asked by stkabirdin9380, 10 months ago

If 27 men can do a certain piece of work in 15 days then how many days will 18 men do it

Answers

Answered by Fatimahaider
1

Answer:

10 days

Step-by-step explanation:

27 men can do a certain piece of work in = 15 days

1 men can do a certain piece of work in = 15/27

18 men can do a piece of work in = 15/27×18

= 10 days