if 27 men can finish a part of work in 64 days,then how many more men are needed to finish the same part of work in 36 days
Answers
Answered by
2
Answer:
21 men
Step-by-step explanation:
* As it is clearly a case of inverse variation thus we wrote 27 X 26 = x X 36
* 1 = 27
* 2 = x = 48
* 48-27 to find the number of extra men required to finish the part of work in 36 days
Attachments:
Answered by
0
Answer:
21 days
Step-by-step explanation:
64 days = 27 men
36 days = x men
so in this case its inverse variation
64×27 = 36×x
64×27/36 = 48
so 48 men are required
so more men = 48-27=21