If 28 men can do a piece of work in 65 days .How many men will do it in 35 days
Answers
Answered by
10
Hey!
_________________
INVERSE PROPOTION
Days taken to complete work by 28 men = 65
Days taken to complete work by x men = 35
Now,
28 × 65 = 35 × x
1820=35x
1820/35=x
x= 52
52 men will complete the work in 35 days.
__________________
Hope it helps...!!!
_________________
INVERSE PROPOTION
Days taken to complete work by 28 men = 65
Days taken to complete work by x men = 35
Now,
28 × 65 = 35 × x
1820=35x
1820/35=x
x= 52
52 men will complete the work in 35 days.
__________________
Hope it helps...!!!
Nikki57:
ans is correct?
Answered by
23
It is a case of inverse proportion...
Let the no. of men to do piece of work in 35 days be x
Therefore :
28 : x
65 : 35
Inverse proportion = x1×Y1 = x2× Y2
= 28×65 = 35x
1820. = 35x
x = 1820/35
x. = 52
Therefore 52 men are required...
Let the no. of men to do piece of work in 35 days be x
Therefore :
28 : x
65 : 35
Inverse proportion = x1×Y1 = x2× Y2
= 28×65 = 35x
1820. = 35x
x = 1820/35
x. = 52
Therefore 52 men are required...
Similar questions
Math,
8 months ago
Computer Science,
8 months ago
Math,
8 months ago
Science,
1 year ago
Political Science,
1 year ago
Physics,
1 year ago
English,
1 year ago
Math,
1 year ago