If 3 men and 4 women can finish the work in 24 days, 4 men and 8 women can finish the same work in 15
days, in how many days will it take for one man alone to finish the same work?
240 days
o 200 days
CO2
150 days
0 120 days
Answers
Answer:
Option D : 120 days
Step-by-step explanation:
Given:
- 3 men and 4 women can complete a work in 24 days
- 4 men and 8 women can complete the work in 15 days
To Find:
- Days taken by one man alone to complete the work
Concept:
Create linear equations in two variables using the given data. Solving it by elimination method we get the value of the variables.
Solution:
Let work done by 1 man in one day = x
Let work done by 1 woman in one day = y
Hence by first case,
3 men and 4 women finish the work in 24 days
3x + 4y = 1/24--------(1)
Now by second case,
4 men and 8 women finish the work in 15 days
4x + 8y = 1/15--------(2)
Multiply equation 1 by 2
6x + 8y = 2/24
6x + 8y = 1/12 ------(3)
Solve equation 2 and 3 by elimination method,
6x + 8y = 1/12
4x + 8y = 1/15
2x = 1/12 - 1/15
2x = (15 - 12)/180
2x = 3/180
2x = 1/60
x = 1/120
Hence days taken by one man alone to complete the work = 120 days
Hence option D is correct.
Given :- If 3 men and 4 women can finish the work in 24 days, 4 men and 8 women can finish the same work in 15
days, in how many days will it take for one man alone to finish the same work ?
A) 240 days
B) 200 days
C) 150 days
D) 120 days
Solution :-
given that,
→ 3M + 4W can finish the work in = 24 days.
and,
→ 4M + 8W can finish the same work in = 15 days.
since work is same in both case , comparing work we get,
→ 24(3M + 4W) = 15(4M + 8W)
→ 72M + 96W = 60M + 120W
→ 72M - 60M = 120W - 96W
→ 12M = 24W
→ M/W = 24/12
→ M/W = 2/1
→ M : W = 2 : 1 .
So, Let Efficiency of each Men is 2 unit of work per day and Efficiency of each women is 1 unit of work per day.
Than,
→ Total work = 24(3M + 4W) = 24(3*2 + 4*1) = 24(6 + 4) = 24 * 10 = 240 units .
Or,
→ Total work = 15(4M + 8W) = 15(4*2 + 8*1) = 15(8 + 8) = 15 * 16 = 240 units.
Therefore,
→ Total work done by 1 man alone = (Total work) / (Efficiency of 1 man per day) = 240 / 2 = 120 days. (Option D) (Ans.)
Hence, 1 man alone can finish the same work in 120 days.