If 3 men can dig a 3 x 2 x 4 meter hole in 20 minutes, how long will it take 6 men to dig a 4 x 4 x 3 meter hole?
5 minutes
10 minutes
Answers
Answer:
20
Step-by-step explanation:
Given If 3 men can dig a 3 x 2 x 4 meter hole in 20 minutes, how long will it take 6 men to dig a 4 x 4 x 3 meter hole?
Now 3 men will dig 24 m^3 in 20 minutes
So we need to find 6 men will dig 48 m^3 in ?
We will consider as 3 men, so
3 men will dig 24 m^3 in 20 min
same 3 men will dig 48 m^3 in 48 x 20 / 24 = 40 min
Therefore 3 men will dig in 40 min
6 men will dig in 3 x 40 /6
120 / 6 = 20 min
Answer:
If 3 men can dig a 3 x 2 x 4 meter hole in 20 minutes, then 6 men will take to dig a 4 x 4 x 3 meter hole = 20 mins
Step-by-step explanation:
3 men can dig a 3 x 2 x 4 meter hole in 20 minutes,
3 * 2 * 4 = 24 m³
3 man can dig 24 m³ in 20 minutes
1 man can dig 24 m³ in 20 * 3
6 men can dig 24 m³ in 20*3/6 = 10 mins
6 man can dig 1 m³ in = 10/24 mins
to be dig = 4 * 4 * 3 = 48 m³
6 man can dig 48 m³ in = (10/24) * 48 = 20 mins