if 3 men can do some construction work in 8 days, how long will 4 men take to complete the same work with the same ability
Answers
Answered by
10
Answer:6
Step-by-step explanation:
3 men in 8 days
1 man in 24 days
4 men in 6 days
Answered by
10
4 men take 6 days to complete the same work
Step-by-step explanation:
3 men can do some construction work in days = 8
1 man can do some construction work in days =
4 men can do some construction work in days == 6 days
Hence 4 men take 6 days to complete the same work