If 3 men or 4 women can complete a certain job in 43 days,how long will 7 men and 5 women take to complete it?

Answers

Answered by ankit6390
1
4women= 3 men
5..............= 3×5/4=15/4men
now, 7men+5women= 7 men+15/4 men= 43/4 men

a/q
3men complete in 43 day
1 ...............................43×3 day
43/4 ......................43×3×4/43=12 day