Math, asked by xursua6441, 11 months ago

If 3 men or 5 boys can do a piece of work in 11 days. How long would 1 man and 2 boys take to complete the same work

Answers

Answered by aditya1843
5
I don't know the answer

tahseen619: rewrite the question please
Answered by wifilethbridge
6

1 man and 2 boys take 15 days to complete the same work

Step-by-step explanation:

3 men or 5 boys can do a piece of work in 11 days.

3 men = 5 boys

1 man = \frac{5}{3} boys

1 man and 2 boys =\frac{5}{3} boys + 2 boys = \frac{5+6}{3}=\frac{11}{3} boys

5 boys can do a piece of work in days = 11

1 boy can do a piece of work in days = 5 \times 11

\frac{11}{3} boys can do a piece of work  =\frac{5 \times 11}{\frac{11}{3}}=15

Hence 1 man and 2 boys take 15 days to complete the same work

#Learn more:

2 men and 3 boys together can do a piece of work

in 8 days. The same work is done in 6 days by

3 men and 2 boys together. How long would 1 boy

alone and 1 man alone take to complete the work

independently?

(1) 40 days, 120 days

(2) 120 days, 40 days

(3) 20 days, 120 days

(4) 120 days, 20 days​