Math, asked by Deepanjan16, 1 year ago

If 3 men or 6 boys can a work in 20 days. How many days will the work will be completed by 4 men and 12 boys?

Answers

Answered by 1Gaurav11
1
If  3 men or 6 boys can do piece of work in 20 days.how many days will 6 men and 8 boys take to do the same work?
:
Given, work can be done by:
3*20 = 60 man-days
or
6*20 = 120 boy-days
therefore
60 md = 120 bd
divide by 60
md = 2bd
:
how many days will 6 men and 8 boys take to do the same work?
let d = no. days to accomplish this in terms of man-days
we know that 8bd = 4 md; therefore
6d + 4d = 60
10d = 60
d = 6 days for 6 men and 8 boys to do the job


thanks;)
Answered by Anonymous
1
If 3 men or 6 boys can a work in 20 days. How many days will the work will be completed by 4 men and 12 boys?
answer is in the above picture.

HOPE IT HELPS YOU