If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work ?
Answers
Answered by
28
Answer:
The work can be completed in 20 days by 3 men or 6 boys.
Hence the capacity of 3 men = the capacity of 6 boys.
Hence if 4 men and 12 boys do the work together, than it is equivalent to,
4 + 6 = 10 men
Now the work quantum = 3 *20 = 60
Hence if now equivalent to 10 men are doing the work, then
No. of days = 60/10 = 6
Answered by
1
3 men = 6 boys
4 men = x 4 = 8
Total boys in second case :
= 4 men + 12 boys = 8 + 12 = 20 boys
6 boys can do a piece of work in 20 days
Then let 20 boys will do the same work in x days
∴ 6 : 20 :: 20 : x
(More boys, less days)
⇒ 6 : 20 :: x : 20
(By inverse proportion)
X = (20 × 6)/20
= 6 days
∴ They will do the work in 6 days